Project Plans & Updates

Project Updates

126th Street

Phase I, II & III construction on 126th Street & SR 37 have been completed. These phases consisted of temporary pavement and crossovers on SR 37 along with widening 131st Street at Parkside Drive and the construction of the bridge on the west side of 126th Street & SR 37. Utility relocation has been completed as well in this intersection. The next phase of construction will be the excavation of the intersection and construction of the bridge on the east side of 126th Street.

Phase IV of construction is underway with traffic currently shifted to the west. Traffic is now restricted on 126th Street across SR 37 with only right in and right out. Northbound SR 37 traffic will not have access to 126th Street and will shift to Southbound lanes. Two lanes will remain in each direction. 126th Street from the Nickel Plate Trail crossing to Ford Drive will close on Monday, August 10 and is anticipated to reopen in late September. Motorists are encouraged to use 131st Street while this is under construction. See the Detour Route

DETOUR ROUTE Opens in new window

146th Street

Phase 1 construction on 146th Street & SR 37 has been completed. This phase consisted of the temporary pavement on SR 37 and 146th Street and median work. Phase II construction is underway with traffic moved to the interior lanes and all left turns restricted on SR 37 and on 146th Street as work begins on constructing the ramps. Through traffic and right turns on SR 37 and 146th Street will remain open during this phase. Drivers are encouraged to seek alternate routes for all left turn access. This phase is anticipated to be completed by the end of November. See the Alternate Route Map.

alternate route map Opens in new window

Project Plans

Project Renderings

Additional Info