Timeline

The final design of the SR 37 Improvement Project will be determined over the next two to three years as environmental and design studies are completed with opportunity for public input. Once design is complete, the construction period is expected to last approximately three years.

Preliminary Timeline

This preliminary timeline is subject to change at any time without notice.

Capture September 2022

Project Milestone Dates

  • Design Begins – May 2016
  • Survey Complete – September 2016
  • Preliminary Field Check – January 2017
  • Public Hearing – May 2017
  • Geotechnical Field Work – Summer 2017
  • Final CE Approval – April 2018
  • Design – In progress
  • Drainage Trunk Line Letting – September 2018
  • 126th Street Letting – July 2019
  • 146th Street Letting – February 2020
  • 131st Street Letting – December 2020
  • 141st Street Letting – Summer 2023